8月19日,隨著(zhu)(zhu)一聲合閘聲響,二公司萬華熱電項(xiang)(xiang)目(mu)部,提(ti)前一天圓滿(man)完成8.20倒送(song)電任務,標志著(zhu)(zhu)該(gai)項(xiang)(xiang)目(mu)部已進入(ru)單調階段。
據悉,該項目電氣安(an)裝從5月21日正式(shi)開工(gong)(gong)(gong)(gong)(gong),至(zhi)本(ben)次倒送電成功共安(an)裝調(diao)試高(gao)壓柜30面、低壓配電柜40面、保(bao)護柜20面、2套電池(chi)組、40多(duo)面DCS盤柜以(yi)及(ji)2臺干(gan)式(shi)變壓器(qi),各種規格橋架安(an)裝共2000多(duo)米(mi),敷設電纜8萬多(duo)米(mi),其中包括2000多(duo)米(mi)3×185的高(gao)壓電纜。本(ben)次安(an)裝存在工(gong)(gong)(gong)(gong)(gong)期(qi)緊、施工(gong)(gong)(gong)(gong)(gong)場地狹(xia)小,多(duo)家單位(wei)交(jiao)叉施工(gong)(gong)(gong)(gong)(gong),設備(bei)材料到貨(huo)緩慢,設計圖(tu)紙與現場施工(gong)(gong)(gong)(gong)(gong)情況不符,且與二期(qi)生產區域(yu)交(jiao)叉施工(gong)(gong)(gong)(gong)(gong)等情況。該項目部積極與業主、土建單位(wei)、設計單位(wei)溝通,班組施工(gong)(gong)(gong)(gong)(gong)人(ren)員加班加點,終(zhong)于順利提前完(wan)成了施工(gong)(gong)(gong)(gong)(gong)目標,為后期(qi)的設備(bei)單調(diao)提供了條件。
后期,該項(xiang)目成(cheng)員將(jiang)繼續保持(chi)這(zhe)種吃苦耐勞,不畏艱難的精神,確保10.1點爐(lu)目標的順利完成(cheng)。(李想)